WAPDA to add 2485 MW from 3 major projects

WAPDA to add 2485 MW from 3 major projects

ISLAMABAD: (APP) Water and Power Development Authority (WAPDA) will add 2485 MW hydel electricity to the National Grid till mid 2018.

The said quantum of electricity would be added to the system with completion of three under-construction hydropower projects from end 2017 to mid 2018, said a statement issued on Friday.

These projects include the 969 MW-Neelum Jhelum Hydropower Project, the 1410 MW-Tarbela 4th Extension Project and the 106 MW-Golen Gol Hydropower Project. After completion, these projects will cumulatively contribute 9.432 billion units of low-cost and environment-friendly hydel electricity to the system every year.

It is pertinent to mention that WAPDA projects were marred with delays due to certain reasons, and had missed timelines of their completion, the statement claimed.

After assuming the charge of the office in August 2016, the incumbent WAPDA Chairman Lt Gen Muzammil Hussain (R) re-strategized WAPDA's priorities to complete its under-construction projects in the shortest possible time, and initiate construction work as early as possible on ready-for-construction projects, the statement said.

Because of the active persuasion of WAPDA Chairman and an effective monitoring mechanism in place, WAPDA projects are now back on track.

The hurdles in the way to implementation of the under- construction WAPDA projects have been removed, and these are now heading towards completion at a good construction pace.

First unit of Tarbela 4th Extension will be completed by end 2017, whereas two remaining units during high water flow season in 2018.

Likewise, first unit of Neelum Jhelum Hydropower Project will start electricity generation by end February 2018, second unit in mid-March 2018 and the third and fourth units will be completed in April 2018.

Similarly, first unit of Golen Gol Hydropower Project will be inaugurated in December this year, while overall completion of this project is scheduled in August 2018.

Kachhi Canal Project is being completed in phased manner. The Phase-I will irrigate 72,000 acres of land after its completion in the far flung and backward areas of Dera Bugti district in Balochsitan - 55,000 acres by end August 2017 and another 17,000 acres by end December this year.

The issue of land acquisition for Dasu Hydropower Project, which was pending for the last two years, has been resolved by signing an agreement with 80-member Jirga of the local notables of Kohistan district in December 2016 for smooth and speedy acquisition of land.

Two contracts worth about Rs.180 billion have also been awarded for main civil works of the project. For the 128 MW-Keyal Khwar Hydropower Project, the contractor has been mobilized to the site for start of construction work on the project. Also, construction has commenced on Kurram Tangi Dam (Stage-I) in the current month.

In the wake of approval of the Financial Plan by Prime Minister Muhammad Nawaz Sharif in November 2016, WAPDA was making concerted efforts to award the contract for main works of Diamer-Basha Dam Project by end 2017.

Mohmand Dam Project is also being actively pursued to start construction work as early as possible.