Chitral Hydel Power Station s status

Chitral Hydel Power Station s status

ISLAMABAD (APP): The power generation capacity of Chitral Hydel Power Station would be enhanced from existing one megawatt to five megawatt at a cost of Rs 2.2 billion.

The capacity enhancement project has approved by the Central Development Working Party (CDWP) in its recently held meeting, said official sources in the ministry of planning, development and reforms here.

KPK Government completes 100 mini-micro hydel projects in backward areas

According to details, the PC-I of the project was submitted to the Ministry of Water and Power after the power demand in Chitral area increased and there was a dire need to upgrade the capacity of existing Hydel Power Station at Chitral.

The concept paper of the project was forwarded to Ministry of Planning, Development and Reforms on November 11,2014 for approval.

The existing 1.0 MW Chitral Hydel Power Station is located on the right bank of Lutkho River, 5 Km upstream of Chitral City.

The Project was commissioned in 1975 by diverting the flows of Lutkho River through 3.72 Km long channel and installing 2 units of 200 KW and 2 units of 300 KW each.

Golan Goal Hydel Power Project : Construction status

The power generated from Chitral Hydel Power Station is supplied to Chitral City through 11 KV Transmission Line.

In the initial construction phase of Project, limited flows of Lutkho River were diverted to Power Channel for generation of 1 MW only.

However the river has abundant flows which can be utilized for Power Generation by constructing a small diversion weir, remodeling of power channel and fore bay and installation of new penstocks and additional units. It is estimated that the Power can be enhanced up to 5 MW.

WAPDA had preliminary studies for the proposed up-gradation. Topographic Survey, Geological Mapping for weir Intake, Power Channel and Power House areas and drilling at weir and Power House area were carried out. Tender Design Report has been completed by Hydro Planning WAPDA in May, 2012.

Mangla Hydel Power Station up-gradation plan

The estimated cost of the Project is US$ 15 million and completion time is 3 years.