ISLAMABAD: Supreme Court gives a new deadline for Orange Line Metro Trainproject Lahore.
Supreme Court on Friday directed to complete work on Orange Line MetroTrain project till May 20.
A two-member bench of the apex court comprising Justice Gulzar Ahmad andJustice Ijaz-ul-Ahsan was hearing the case.
During the proceedings, Justice Gulzar Ahmad, while expressing anger onproject director Fazal Haleem, said that the work on the project has beendelayed due to him.
He remarked that billions of rupees have been spent on the project, addingthat this is a project of national interest.
The bench sought guarantees of Rs10 million each from the threeconstruction companies.
It said that the guarantees will be seized if the construction work on theproject was not completed until the 20th of next month.