$7.8 billion most deadly American warship faces a setback
Shares
ISLAMABAD - The USS Zumwalt (DDG-1000), the first of three new guided missile destroyers for the US Navy, won’t be delivered with complete combat capability until the first quarter of next year, six years behind schedule.
Colleen O'Rourke, a Navy link spokesperson, confirmed to Stars and Stripes link this week that the $7.8 billion USS Zumwalt was supposed to reach full combat capability last month. The destroyer was initially planned to reach full combat capability five years ago and be fully operational three years ago.
"While combat system testing has made significant progress, Zumwalt continues to work through first-in-class integration and shipboard test challenges," O'Rourke said.
The destroyers are undergoing a phased delivery strategy, according to Stars & Stripes link, with hull and mechanical and engineering installation being completed at General Dynamics Bath Iron Works in Maine, followed by testing on the East Coast and combat system activation in California by defense contractors Raytheon and BAE Systems.
Once all of the ships’ combat systems have been installed and tested, they will be considered ready for final delivery. At present, the first two destroyers, the Zumwalt and the USS Michael Monsoor, are active.
Shelby Oakley, an acquisition director with the Government Accountability Office (GAO), also confirmed to Stars & Stripes link that the delays “continue to stem from the same, numerous difficult issues the Navy has faced on DDG-1000 for some time that are a result of concurrently attempting to prove out and build a very complex ship.” The GAO said in an April report that the Navy link is “still working to correct” 320 “serious deficiencies” on the ship.
According to the US Navy, the Zumwalt is the “largest and most technologically advanced surface combatant in the world” and will be able to perform a “range of deterrence, power projection, sea control and command and control missions.”