CPEC Western Route projects status update

CPEC Western Route projects status update

ISLAMABAD: (APP) Construction of Western Route of the China-Pakistan Economic Corridor (CPEC) is included among the top priorities of the government.

An official of National Highway Authority (NHA) told APP on Tuesdsy that construction of Hakla-D.I.Khan has begun.

Prime Minister Muhammad Nawaz Sharif performed the ground breaking of Hakla-Dera Ismail Khan Motorway.

This project, he said, is an important part of Western Route of CPEC.

He said the 285 km-long Hakla-D.I.Khan Motorway will be completed within two years at a cost of more than Rs 142 billion.

He said the project alignment started at Hakla, near Tarnol interchange on M-1 and passed through Fateh Jhang, Mianwali,Kundal and ends at Yarak at Indus Highway (N-55).

He said the alignment of motorway passed through developing areas and its construction will generate new employment opportunities.

The NHA official said ground breaking of the up-gradation of Zhob-Mughalkot section was performed by Prime Minister Nawaz Sharif in December 2015.

CPEC first Chinese shipment arrives in Pakistan

He said up-gradation of Zhob-Quetta highway had also been realized and work on Sorab-Hoshab section was in progress.

He said 193 Km Hoshab -Turbat-Gwadar portion had been completed and rehabilitation of D.I.Khan-Mughalkot section of N-50 would be completed by 2018.

He said dualization of 531 km D.I.Khan to Kuchlak section of N-50 would be operational by 2020.

About dualization of 211 km Quetta-Kalat-Surab section, he said that the project was planned to be completed by 2020.

CPEC western route: 285 Km DI Khan-Hakla motorway starts